DETAILED ENGINEERING AND PROJECT MANAGEMENT


Existing Unit of Saurashtra Cement Ltd. at Ranavav, Gujarat, India

Saurashtra Cement Ltd., promoted by The Mehta Group International Ltd., having over four decades of experience in the cement industry is a major player in the western India. Apart from cement, the group has interest in Sugar, Agriculture, Cables, etc. in India as well as a number of other countries.

The plant with installed capacity of 0.87 mio tons per annum, supplied by FULLER (USA) was commissioned in 1984. The plant capacity has been enhanced in two phase as under :

  • Phase I     :        1.094 mio tons per annum
  • Phase II : 1.294 mio tons per annum

Owner

Saurashtra Cement Limited

Consultant

Holtec Consulting Private Limited, India

Supply of Main Machinery

FL Smidth, Denmark, Fuller USA, IKN Germany, Fuller India and Larsen & Toubro, India

 

Special Features

  • Installation of Semi-Mobile Crusher and Limestone Preblending stockpile
  • Upgradation of Raw Mill by replacing Conventional Rotary Classifier with High Efficiency Separator and Mill Cyclones with Hurriclone Cyclones
  • Installation of Bag House for Kiln/Raw Mill
  • Installation of 5 Stage PH/PC parallel to the existing PH
  • Replacement of existing pneumatic transport system for raw meal with bucket elevators
  • Installation of gravimetric system for kiln feed and fine coal control
  • Part replacement of existing Cooler with new generation IKN Pendulum Cooler
  • Installation of state-of-art Plant Automation and Control System
  • New Cement Mill for clinker grinding
  • New DG Set to meet emergency power needs

 

Scope of Consulting Services

  • Preparation of Techno-economic Feasibility Report for Modernisation/Expansion of the plant and discussions with Financial Institutions
  • Basic Engineering, Procurement, Detailed Engineering & Inspection
  • Project Implementation & Management
  • Supervision of Construction, Erection, Trial Runs and Commissioning

 

Key Project Data

Quantities

Project Drawings

1080 Nos.

Suppliers

30 Nos.

Execution Agencies

3 Nos.

New Equipments

Crusher

1,000 tph

Cement Mill

150 tph

DG Set

6.4 MW

Capacity Enhancement

Raw Mill

220 – 280 tph

Kiln

2,500 – 3,750 tpd

Achievements

  • Reduction in Specific Power Consumption (From 110 KWh/t to 88 KWh/t of cement)
  • Reduction in Specific Fuel Consumption (From 830 Kcal/kg clinker to 720 Kcal/kg clinker)
  • Reduction in dust emission levels (From 240 mg/Nm3 to 50 mg/Nm3.
  • High Quality Product (53 Grade cement in place of earlier 33 Grade)
  • Optimised Plant Operations (Plant availability of 330 days/annum at 90% capacity utilisation as against earlier plant availability of 310 days/annum at 85% capacity utilisation)
22 similar Plant Modernisation/Upgradation/Conversion assignments executed