| 2.0 mio tons per annum AP Cement Project at Tadipatri, Andhra Pradesh,
India 
Key Project Data
| Topographical survey |
10 sq km |
| Geological mapping |
10 sq km |
| Core drilling |
2700 m |
| DTH drilling |
1500 m |
| Geo Electric Soundings |
120 nos |
Sample preparation
Individual
samples
Composite samples
|
4500 nos
1000 nos |
| Sample Analysis |
| Individual (for TC/MC) |
4500 nos |
| Composite (Major &
Minor oxides) |
1000 nos |
| Environmental Data
Collection |
Plant |
Mines |
| Air sampling (nos) |
288 |
48 |
| Water (nos) |
60 |
36 |
| Soil (nos) |
16 |
4 |
| Noise (nos) |
20 |
16 |
| Meteorological data
(days) |
365 |
| Land use survey |
30 sq km |
| Socio-Economic survey |
120 sq km |
|
M/s Larsen & Toubro Limited is a diversified business conglomerate in India
with interest in cement manufacture, plant and machinery for diverse industries,
construction, IT, Telecom, etc. In order to expand their capacity L&T engaged services
of Holtec to conduct raw material identification, evaluation and management studies for
establishment of a green field 2.0 mio tons per annum cement project at Tadipatri, Andhra
Pradesh, India.Owner
Larsen & Toubro Ltd. (L&T)
Consultant
Holtec Consulting
Private Limited, India
Scope of
Consulting Services
- Conduction of site identification study for
delineation of limestone bearing area for establishment of Cement Project.
- Conduction of detailed geological
investigation including topographical survey, geological mapping, core/DTH drilling,
sampling and chemical analysis.
- Preparation of Prospecting Report for the
deposit.
- Preparation of Statutory Mining Plan and
its approval from Indian Bureau of Mines.
- Collection of baseline environmental data
for both proposed mine and plant and preparation of Environmental Impact Assessment (EIA)
and Environmental Management Plan (EMP) Report for both plant and mines.
- Environmental Clearance of the Project from
Andhra Pradesh State Pollution Control Board and Ministry of Environment & Forests
(MOEF) for plant and mines.
- Computer Aided Deposit Evaluation (CADE) and
Quarry Scheduling Optimization (QSO) of deposit.
- Geo-electric Survey for soil profiling and
detection of karst topography.
- Topographic survey for plant, colony and
mines and plant corridor area.
- Hydrological survey for mines and plant
areas.
Salient Features
- Turnkey raw material identification,
exploration and management services with single point responsibility.
- International norms adopted for deposit data
generation.
- First plant of 2.0 mio tons per annum
successfully operating for last 3 years.
- Second plant of 2.0 mio tons per annum
already planned for implementation.
|